Capstone Insights Q4 2026

The Capacity Equation: Labour, Cost and Productivity in Canadian Construction

By Sébastien Ameur | Managing Editor


Lumber, steel beams, blueprints and a hard hat on a construction site at sunset
The supply side: labour, materials and the trade regime now shaping Canadian build costs

Canada's build agenda now depends less on demand than on whether the industry can supply the people, materials and output per hour to deliver it. Every measure of that supply side moved in the third quarter of 2026, and most of them moved against the builder.

On October 29, Statistics Canada reported that non-residential building costs rose 4.3% over the past year and residential costs rose 2.7% (Statistics Canada, Building construction price indexes, Q3 2026). The day before, the Bank of Canada raised its policy rate by 25 basis points to 2.50%, its first increase after seven consecutive holds, and projected inflation to remain around 3% through much of 2027 (Bank of Canada, October 28, 2026). Those two releases frame the quarter. Construction in Canada is now operating with rising input costs, a tighter labour pool, a heavier trade regime and more expensive money at the same time.

This piece examines each of those constraints in turn, using the newest data available as of late October 2026.

The workforce: a full hiring decade ahead

BuildForce Canada's 2026 to 2035 outlook, released in July, is the reference point for the labour question. Construction accounts for 7% of Canadian GDP and employs 1.6 million people, about one in every 13 working Canadians. BuildForce projects that roughly 135,000 workers will retire over the forecast period, and that the industry will need to hire 306,200 workers in total, about 271,900 of them new entrants aged 30 and under. Even under heightened recruitment, it projects a shortfall of up to 34,300 workers (BuildForce Canada, Construction and Maintenance Looking Forward 2026-2035).

The composition of demand matters as much as the total. BuildForce projects residential construction employment to fall 4% by the end of the decade relative to 2025, as residential investment contracts from 2026 to 2028. Non-residential employment is projected to rise 6% by 2035, supported by roughly 800 major projects worth more than $500 billion. The labour pressure, in other words, is shifting toward civil, industrial, energy and institutional work, which draws on a different and often more specialized trade mix.

The current data already shows a tight market. Construction's unemployment rate fell to 3.8% in September 2026, the lowest since October 2024, with construction employment up 20,400 (1.2%) year over year (BuildForce Canada analysis of the September 2026 Labour Force Survey). The national picture came in weaker: total employment fell 68,000 in September and the overall unemployment rate stood at 6.5% (Statistics Canada, Labour Force Survey, September 2026). Construction is holding its workers while the broader economy softens.

The detail beneath the headline is the concern. Employment among construction workers aged 15 to 24 fell 2.7% year over year in September, while employment among workers 55 and older rose by 8,400. The regional split is equally sharp: Alberta added 17,900 construction jobs (6.9%) and Ontario 11,600, while Quebec lost 15,800 (4.7%) and British Columbia 8,300 (3.1%). A workforce that is ageing at the top and thinning at the entry point is the opposite of what a decade of 306,200 hires requires.

The training pipeline

The apprenticeship system is drawing more people in but is not yet converting them at the rate needed. New apprenticeship registrations reached 101,541 in 2024, up 5.9% and the highest since 2008, and registrations in the construction trades group rose 24.2%. Certifications, however, rose only 1.0% to 46,971, still 9.6% below pre-pandemic levels (Statistics Canada, Registered Apprenticeship Information System, 2024). Registrations are a leading indicator; certifications are what reach the jobsite as journeypersons. The gap between the two is a lag of several years that the industry cannot shorten by recruitment alone.

Immigration: a smaller, more targeted inflow

Newcomers made up about 20% of the construction labour force in 2025, compared with 28% across all occupations, according to BuildForce. The federal 2026 to 2028 Immigration Levels Plan holds permanent resident admissions flat at 380,000 a year, shifts the economic class to 64% of admissions by 2027, and reduces temporary resident arrivals to 385,000 in 2026 and 370,000 in each of 2027 and 2028 (IRCC, 2026-2028 Immigration Levels Plan). Statistics Canada counted 2,779,774 non-permanent residents on July 1, 2026, down 0.7% from the previous quarter (Statistics Canada, population estimates, Q3 2026).

Within a smaller overall intake, the trades channel has widened. The Express Entry trade occupations category issued 3,500 invitations on October 1, 2026 at a cutoff score of 476, after 3,000 invitations in April and 1,250 in September 2025 (Moving2Canada, Express Entry trades draw tracker). The policy direction is fewer temporary arrivals overall, with a larger share of selection pointed at skilled trades.

Productivity: the constraint underneath the others

If the industry cannot easily add workers, output per worker becomes the decisive variable, and it has been moving the wrong way for two decades. A February 2026 study by Statistics Canada and CMHC found that real gross output per worker in residential construction fell 37.3% between 2001 and 2023, an average decline of 2.1% a year. Over the same period, business-sector productivity rose 12.5%. Toronto recorded the steepest decline, at 3.4% a year (Statistics Canada and CMHC, residential construction productivity, February 2026).

The recent period is the steepest part of the slide. CMHC estimates that residential construction productivity grew 1.5% a year from 2008 to 2019, then fell 3.8% a year from 2019 to 2024, as hours worked rose 3.9% a year while real value added was essentially flat. CMHC attributes $6 billion to $8 billion in added costs, and up to 20% of new home price increases over that period, to the productivity loss (CMHC, Framework for Change: Productivity in Housing Construction). The Centre for the Study of Living Standards reaches a similar figure, placing 2024 output per hour 8% below its 2000 level and the cost to the average buyer at $24,000 to $31,000 (CSLS Research Report 2025-08).

The structure of the industry is part of the explanation. Firms with fewer than 20 employees still accounted for 66.1% of residential construction employment in 2023, down from 79.6% in 2001. Small firms carry less capital per worker and have fewer means to standardize, which limits the gains available from repetition.

Costs: tariffs reach the price indexes

The third-quarter cost data shows where the trade dispute has entered building budgets. In non-residential construction, the largest quarterly increases were in structural steel framing (3.3%), conveying equipment (3.1%) and metal fabrications (2.1%). In residential construction, metal fabrications rose 2.4%. Statistics Canada directly cites Canada's retaliatory tariffs on US goods, which took effect September 8 at rates from 15% to 50%, including 50% on certain steel and aluminum products, alongside higher fuel, transportation and skilled-labour costs.

Cost growth is also uneven by region. In the third quarter, residential costs rose 2.3% in Québec City and 1.8% in Regina, compared with 0.4% in Toronto and 0.2% in Vancouver. Non-residential costs rose 2.4% in both Québec City and Regina and 2.0% in Montréal. Altus Group's 2026 Canadian Cost Guide, built on 6,652 projects worth $573 billion, similarly reported 2025 cost increases of 4% or more in Calgary, Edmonton, Montreal and Winnipeg, and declines in Toronto and Vancouver, with skilled labour identified as the leading 2026 risk in Alberta (Altus Group, 2026 Canadian Cost Guide insights). Where activity is strongest, costs are rising fastest.

Upstream, input prices are rising faster still. In September, Statistics Canada's Industrial Product Price Index was up 14.5% year over year and the Raw Materials Price Index was up 27.0%, with unwrought copper up 46.3%, unwrought aluminum up 26.9% and diesel up 106.1% (Statistics Canada, IPPI and RMPI, September 2026). Much of that has not yet passed through to the building indexes, which move more slowly because they measure contracted and installed costs.

The trade regime, measure by measure

The tariff environment affecting Canadian construction inputs now runs through several separate instruments.

The trade regime, measure by measure
MeasureInputs affectedCurrent status
US Section 232, steel and aluminumStructural steel, aluminum products and derivatives50% US duty since June 4, 2025; CBP Section 232 derivatives list expanded Aug. 18, 2025 (Blakes)
US Section 232, timber and lumberSoftwood lumber10% US duty since Oct. 14, 2025 (Global Affairs Canada)
US anti-dumping and countervailing dutiesSoftwood lumberAll-others combined rate cut to 24.75% from 35.16% in the seventh administrative review, finalized Oct. 14, 2026 (Global Affairs Canada)
US Section 338About US$20 billion of Canadian goods50% from Aug. 22, 2026; goods already under Section 232 excluded; cement removed Sept. 15 (Davis Wright Tremaine)
Canadian counter-tariffsC$27.6 billion of US goods, including steel, aluminum and wood15%, 25% and 50% tiers from Sept. 8, 2026 (Blakes)
Canadian steel tariff-rate quotasImported steel from non-FTA sourcesYear two from June 28, 2026, with a 50% over-quota surtax (GHY International)

For lumber, the seventh-review result lowers the duty burden, but combined with the 10% Section 232 tariff, the all-others total still stands at 34.75%. The broader framework is also less settled than it was. The United States declined to renew CUSMA at the July 1, 2026 joint review, which moves the agreement to annual reviews while it remains in force to 2036.

On the procurement side, the federal Buy Canadian Policy applies to federal construction and defence contracts of $25 million or more that require at least $250,000 of steel, aluminum or wood, and requires those materials to be made or processed in Canada (Public Services and Procurement Canada). For domestic producers, that creates a protected source of demand. For contractors, it adds a sourcing requirement to bids at a time when domestic capacity in some product categories is already under pressure.

Financing: the cost of starting

The October rate increase adds to financing conditions that were already restrictive for one segment in particular. The Bank of Canada noted earlier this year that lenders typically require about 70% of condominium units to be presold, with buyer deposits of around 20%, before construction financing is released, and that 2025 condominium starts in Toronto were at lows not seen since the 1990s (Bank of Canada, What's behind the slowdown in Toronto's condo market). In the third quarter of 2026, the Greater Toronto and Hamilton Area recorded only 60 preconstruction condo sales, the twelfth consecutive quarter of annual declines (Urbanation, via CP24).

Government charges add a further layer. CMHC's December 2025 analysis placed Toronto's development charges at $130,200 per apartment and $180,600 per single-detached home, compared with $8,584 per apartment in Montreal. In Markham, charges equal 15.7% of a new condominium's price (CMHC, We built this city: development charges).

Industrialized construction as a capacity strategy

The federal response to the productivity problem has centred on how homes are built, not only how many. Build Canada Homes was launched in September 2025 with $13 billion in capital and a mandate that prioritizes factory-built, modular and mass timber methods (Prime Minister's Office). Its August 2026 partnership with the City of Toronto covers nine projects and 1,885 homes, with pilots in volumetric modular, panelized and mass timber construction (Housing, Infrastructure and Communities Canada).

The codes are moving in the same direction. The 2025 National Building Code raises the height limit for encapsulated mass timber construction from 42 metres to 50 metres and adds greenhouse gas emissions as a formal code objective (Urban Development Institute). British Columbia and Ontario already permit encapsulated mass timber buildings up to 18 storeys. Policy analysis is converging on the same list. C.D. Howe's October 2026 report calls for standardized codes, an end to duplicate inspections of modular units and financing and insurance products designed for factory-built housing (C.D. Howe Institute, The Productivity Blueprint).

The argument for industrialized construction is fundamentally a labour argument. Factory production moves work indoors, standardizes repetition and uses fewer site hours per unit, which is the one lever that addresses the workforce gap and the productivity decline at the same time.

Resilience, for now

The stress has not yet produced a wave of failures. The Office of the Superintendent of Bankruptcy recorded 752 construction insolvencies in the 12 months to August 2026, down 5.5% from a year earlier, and 44 in August alone, down 21.4% year over year (Office of the Superintendent of Bankruptcy, August 2026). Contractors are absorbing higher input costs and tighter labour without a rise in business failures, at least through the summer.

What to watch into 2027

The capacity question will be answered in a small number of data series over the next two quarters:

  • Fourth-quarter building cost indexes, the first full quarter in which the September 8 counter-tariffs will register, and whether the gap between input price growth and building cost growth narrows.
  • Youth construction employment in the monthly Labour Force Survey, the clearest early signal of whether the entry pipeline is recovering.
  • Apprenticeship certifications for 2025, expected in Statistics Canada's next RAIS release, against the 9.6% pre-pandemic gap.
  • Bank of Canada decisions in December and January, given a projection of inflation near 3% through much of 2027.
  • Modular and mass timber delivery under Build Canada Homes, measured in completed units, not announcements.

Canada's demand for construction is not in question. Its capacity to supply that construction at a stable cost is, and that is now the defining variable for the industry.